Energean plc (“Energean” or the “Company”)

27 ott 2022
First gas from Karish

London, 26 October 2022 - Energean plc (LSE: ENOG, TASE: )????is pleased to confirm that first gas has
been safely delivered at the Karish field, offshore Israel.
Highlights
First gas has been achieved on the Karish project
Gas is being produced from the Karish Main-02 well and the flow of gas is being steadily ramped
up
Preparation for transmission through the gas sales pipeline is progressing and gas sales to
Energean’s customers are expected to commence in the next couple of days
Karish Main-01 and Karish Main-03 wells are expected to be opened up in approximately two and
four weeks, respectively
The Energean Power FPSO and the sales gas pipeline have an ultimate capacity of 8 bcm/yr. The initial
capacity is up to 6.5 bcm/yr, and commercial gas sales are expected to reach this level approximately four
to six months following first gas. Energean’s growth projects – the Karish North development, the second
oil train and the second export riser – are on track for completion in late 2023, following which Energean
will be able to produce to the full 8 bcm/yr capacity of its infrastructure.
Mathios Rigas, Chief Executive Officer of Energean, commented:
"I am delighted to confirm that Energean has reached first gas at the Karish field, offshore Israel.
“We have delivered a landmark project that brings competition to the Israeli gas market, enhances security
of energy supply in the East Med region and brings affordable and clean energy that will displace coal-fired
power generation, making a material impact to the environment.
“We are committed to reach our medium-term targets of 200 kboed production and $1.75 billion of
annualised EBITDAX and the delivery of the Karish project is a major milestone towards this goal. We are
now focused on ramping up production and delivering the full 8 bcm capacity through our expansion project
to the Energean Power FPSO.”